Commissioning blister packaging machine boot operation steps and principle description

(1) Check the PVC again, the aluminum foil is in place according to the installation requirements, there is no foreign matter in each active part, and there is no foreign matter on the PVC on the platform, and no red indicator light is on the operation simulation disk.
(2) Press the main motor button, the main motor indicates that the green light is on, wait for 5-7 seconds (at this time, each work is fully open and does not move at this time, and the moving feed air clamp is at the nearest end, these two states and The location is the debug origin).
(3) Press the RUN button to indicate that the green light is on, and the device blister packaging machine https://www.hpm.ltd/Products/71/ . At this time, each station remains inactive, moving the gas clamp forward, moving the gas clamp to drive the PVC through the heating plate (see the note 5 for the upper and lower heating plate gap adjustment), the PVC is heated by I, and after reaching the forming station, the feeding mechanism is at the most remote. The forming station is completely closed, the PVC is pressed, the signal is given by the micro switch, the solenoid valve is actuated, the compressed air is given, and the PVC is blown into the same blister as the forming plate. This process is a PVC blister positive pressure forming process.
(4) The moving air clamp continues to drive the PVC forward. When the first molded blister reaches the heat sealing plate, look at the number displayed by the counter. This number is the number of steps in the cycle (the device is often used during the debugging alignment). This figure refers to the position where the forming blister can enter the heat sealing bubble when the forming blister reaches the heat sealing position. For the alignment adjustment process, see Note 6).
(5) The moving gas clamp drives the PVC forward again and reaches the punching knife. The punching station closes the medicine board and is punched out. After the tablet is punched out, it should be symmetrical before and after the position (see Note 7 for adjustment methods). The remaining waste is driven by the waste motor and wrapped around the waste collection station. At this point, the complete motion cycle of the device is completed, and the device continuously completes the process intermittently in the running state.
(6) When the feeding mechanism of the device is at the farthest end, press the parking button and the running green indicator light is off. The farthest end refers to the position where the moving air clamp runs farthest from the threaded ejector. The device stops at the fixed point. The fixed point position means that it is controlled by the signal axis, each workstation is fully opened to the maximum position, and the feeding mechanism returns to the nearest end.
 (7) Clean up the environment and equipment to meet CMP requirements. Put the medicine on the hopper or cloth tray, put down the universal feeder, and open the universal feeder switch to make the universal cutter vertical brush and roller brush rotate normally. Press the running button, the blister packaging machine starts to run for one cycle and confirms that the alignment is correct. Then, the oscillating switch is pulled to make the oscillating disc vibrate the medicine into the forming bubble device and enter the normal production operation state.